skip to main content
Back to Top

“Substantially Complete” is Substantially Uncertain

Nov 30, 2022

It is common for the commencement date of a commercial lease to be tied to a future event, for example, obtaining a building permit, a change of zoning, or site plan approval. Leases that do not have a fixed commencement date sometimes stir controversy over their enforceability. Often, parties to a lease tie the commencement date to the timing of “substantial completion” of certain construction work. In this News ReLease, we are concerned with the assumption that “substantial completion” is a well-defined term of certain meaning.  Unfortunately, that’s not the case.

The Ontario Court of Appeal recently interpreted the meaning of “substantial completion”, in Paletta International Corporation v Liberty Freezers London Ltd. 

Paletta’s Facts: Delays in Substantial Completion

In 2010, the parties entered into an agreement to lease refrigerated premises in which the tenant would warehouse frozen food and carry on its frozen food distribution business. The parties agreed that the “lease shall commence upon substantial completion of the landlord’s work”. The landlord’s work listed several tasks that the landlord was to complete, including ensuring that certain features of the premises were in good working order and “in accordance with the Canadian Food Inspection Agency regulations and specifications”.

The parties set an informal target date of April 2011 for substantial completion of the landlord’s work, but by June 2011, the landlord’s work remained unfinished and the tenant was forced to cancel contracts with important clients. In October 2011, a year after signing the lease, the landlord’s work was still not finished and the tenant demanded a firm commencement date. By the end of March 2012, the tenant was fed up and advised the landlord that it would not proceed with the lease. The landlord nevertheless carried out the remaining work and ultimately found a replacement tenant.  Then the landlord sued the original tenant for lost rent.

In 2019, the trial judge found that the landlord’s work was substantially complete about one month after the tenant walked away from the deal, namely when the project engineers determined that the premises was ready for commercial occupancy in accordance with the Building Code, and only minor work remained. On this basis, the trial judge awarded the landlord about two million dollars in damages.

The Appeal

In a decision released in June of 2021, the Court of Appeal disagreed with the trial judge’s determination of when the landlord’s work was substantially complete. The Court focused on the lease requirement that the landlord’s work be completed “in accordance with the Canadian Food Inspection Agency regulations and specifications”.

The Court of Appeal found that the trial judge conflated substantial completion of the landlord’s work under the Building Code with substantial completion of the work in relation to the Canadian Food Inspection Agency (CFIA) requirements. The Court pointed out that the fact the premises were ready for occupancy did not mean that they were substantially complete as far as CFIA requirements were concerned, most notably with regard to refrigeration components.  It is noteworthy that the term “substantial performance”, not “substantial completion”, is used in some provinces' construction legislation; however, CFIA regulations do not use “substantial completion”. Essentially, the lease called for a concept of “substantial completion” that was not only undefined, but also entailed compliance with a regime that was particular to food handling.

Unfortunately for the landlord, the only evidence it had that its work complied with CFIA requirements was the registration of the premises by the Agency. Registration required that the occupant (who was, by then, the replacement tenant) demonstrate that its operation met the Agency’s standards. Although evidencing CFIA compliance does not depend solely on registration, the landlord could offer no other evidence that the specified work was CFIA compliant.  As a consequence of having to use the replacement tenant’s CFIA registration date to prove substantial completion of the landlord’s work in accordance with CFIA regulations, the Court of Appeal held that the term of the original tenant's lease did not commence until after the replacement tenant was in possession! As a result, the landlord’s claim for lost rent evaporated.

The Key Takeaway

The key takeaway is that the meaning of “substantial completion” of the landlord’s work was interpreted according to the wording of the lease. The parties had not taken the time to define “substantial completion”, but they had described the landlord’s work as having to comply with regulations pertaining to food safety. Thus, any Building Code stage of completion was irrelevant.

Misusing terms such as: “complete”, “substantially complete” and “substantially performed”, can have substantial consequences.

In most provinces, the meaning of “substantially performed” under construction legislation is dependent on the stage of completion of the construction contract. For example, Ontario’s Construction Act defines “substantial performance” to be when the entire improvement or a substantial part of it is ready for its intended use, or is being used for the intended purpose, and the cost to complete the remaining work or remedy deficiencies is not more than 3% of the first $1,000,000.00 of the contract (i.e., $30,000.00), 2% of the next $1,000,000.00 of the contract (i.e., $20,000.00), and 1% of the balance of the contract price.

In some leases, the parties define “substantially complete” to mean a stage of completion when the landlord’s construction has been sufficiently completed to permit the tenant’s construction to commence without material interference from the landlord’s forces. Other times, the parties omit any reference to “substantial”, tying the delivery of the premises to “completion”. Ontario's Construction Act defines completion of a contract to be when the price to complete is not more than the lesser of 1% of the contract or $5,000.00.

There is no one-size-fits-all definition of “substantially complete”, nor is there a generally understood meaning of the term, as none is provided at common law or by statute. If lease outcomes (such as commencement of a fixturing period, commencement of the term, payment of a tenant allowance, etc.) are tethered to “substantial completion”, it is important to focus on what the parties intend to serve as the critical juncture when the event will be considered to have occurred.

What about Enforceability of a Formula-Based Commencement Date?

Interestingly, in Paletta, the determination of the term commencement date based on a formula (retroactively) was simply not an issue.

Click here to view the PDF version of this News ReLease.

This publication is a general discussion of certain legal and related developments and should not be relied upon as legal advice. If you require legal advice, we would be pleased to discuss the issues in this publication with you, in the context of your particular circumstances.

Recent News

Mar 26, 2025

CCAA Keeps Landlords at Bay

The insolvency of the Hudson’s Bay Company (“HBC”), Canada’s oldest corporation and iconic department store, is the most re...

Dec 20, 2024

Top Courts in Ontario and B.C. Confirm Landlord's Rights when Tenant Tries to Dump the Lease

In our February 8, 2024, News ReLease, we reported on The Canada Life Assurance Company et al. v Aphria Inc. (“Aphria”). In that case, the tenant wanted out of its lease and purported to “repudiate”, in an attempt to force the landlord to take the (office) space to market. The landlord took the position that it had no obligation to accept the tenant’s repudiation or look for a replacement tenant, and that the tenant was required to pay rent over the balance of the term.

Oct 04, 2024

Exclusives Under Attack! - Changes to the Competition Act

In our November 29, 2023 News ReLease entitled, ‘Are Exclusive Covenants About to Become Extinct?’, we reported on changes to the federal Competition Act (‘Act’). On December 15, 2024, any agreement in Canada that ‘lessens competition’ may be subject to an order under the Act. Since exclusive use clauses and restrictive covenants may lessen competition, landlords, tenants and property owners agreeing to such terms are exposed to sanction. The Competition Bureau recently published guidelines (‘Guidelines’) outlining its preliminary enforcement approach to what it dubs ‘anti-competitive controls on the use of commercial real estate’. The Guidelines declare that they are intended to help businesses comply with the new law; unfortunately, the Guidelines raise more questions than they answer...